Kent & East Sussex Railway logo
Kent and East Sussex Railway
Quality Assured Visitor Attraction
 

OPERATING DEPARTMENT

 

 

Home
Working Members Area
Working Members Area
Visitor Information
Joining the K&ESR
How to Volunteer
News
Photo Gallery
Technical Area
Signalbox Simulator
Footplate Promotion
Links
Traffic Request Form

Receive an e-mail when this page is updated  

 

GWR Railcar

picture of no. 20

GWR Railcar Update, March 2008

All external roof vents have been grit blasted and powder coated grey ready for fitting at a later date. The interior ceiling vents have also been grit blasted but will be painted later once the correct ceiling shade of cream has been determined from research.
The first of the two engine radiators has been re-assembled with new stainless nuts and bolts. A nominal pressure test will be applied to ensure no leaks are apparent followed by fitting back onto the railcar.
Production of the eighteen replacement valance panel wood frames is in hand. These will then be clad with galvanised sheet steel and fitted below the main frame to cover the mechanical components, engines, radiators gearboxes etc. etc..
The laborious task of replacing the original plate glass of the window top lights in the passenger saloons with safety glass is now in hand. The sourcing of replacement brass screws damaged while dismantling the window frames has also been resolved.

The first of the two engine radiators has been re-assembled with a successful pressure test to ensure no leaks are apparent. The cast iron top and bottom tanks of the second radiator were in very poor condition. On dismantling, holes and flange damage due to age were discovered and they have now been extensively refurbished to correct this corrosion. Re-assembly and pressure testing will follow soon.
Due to unfortunate delays to the completion of the birdcage coach restoration, the planned entry of the railcar into the carriage shed has now been put back to Easter 2008. Once inside, the railcar will remain until the restoration is complete as a combined railcar team and carriage & wagon project. Therefore speeding up the final restoration and ending a rather long project duration of some 20 years.

The production of the eighteen replacement wood frames for the valance panels has now reached number fourteen. Only four to go!
On the south side engine, the transmission shaft assembly including bearings was unfit for further use. A fully refurbished prop shaft has been fitted. This includes new bearings and universal joints.
We are repairing the metal cowling fitted around the south side radiator and this will be fitted very soon.
We are looking forward to the railcar being in the shed by the time of the next issue of “The Tenterden Terrier”. Initially the bogies will be overhauled together with the wheel sets before we are able to focus on the bodywork.

Finally, please consider your financial support for the GWR Railcar Appeal ensuring funding is available to progress the restoration. Our aim is a 1st class project that the Railway owns and will be proud to use in public service.

GWR Railcar Project

Planned Working Dates - January to December 2008.

All dates are Sundays.

January – 13th & 27th.

February – 10th & 24th.
Note: 16th/17th & 23rd/24th February are “A Day Out With Thomas” events.
Only volunteers and paid staff who have had a CRB check are allowed to work anywhere at the Railway on these specified days. There are no exceptions.

March – 9th & 23rd.

April – 6th & 20th.

May – 4th & 18th.

June – 1st & 15th & 29th.
Note: 7th/8th & 14th/15th June are “A Day Out With Thomas” events.
Only volunteers and paid staff who have had a CRB check are allowed to work anywhere at the Railway on these specified days. There are no exceptions.

July – 13th & 27th.

August – 10th & 24th.

September – 7th & 21st.
Note: 20th/21st & 27th/28th September are “A Day Out With Thomas” events.
Only volunteers and paid staff who have had a CRB check are allowed to work anywhere at the Railway on these specified days. There are no exceptions.

October – 5th & 19th.

November – 2nd & 16th & 30th.

December – 14th & 28th.

The planned entry date for the GWR Railcar into the carriage shed will be during the period Easter to June 2008 and it will remain in the shed until the project is finished.

The railway will again be running open days to give our visitors the opportunity to see behind the scenes. These are Sunday April 6th 2008 and Monday May 26th 2008. We intend to be in attendance to show our visitors the railcar, explain the project and possibly recruit more volunteers.

Andrew Webb 7th January 2008.


E- mail the Webmaster with questions or comments about this web site.
Last modified: May 15, 2007